Got the boxes all cleaned up for all of the new gaskets as well as got the roller rockers installed,
Filled the valve reliefs with clay to check piston to valve clearance.
Lifters have been bled down and installed and the motor is ready to be turned over.
Here is what it looked like after the motor was rolled over.
Here is how I measured the thickness of the clay. I have over .100 on the intake and the exhaust was not even close. I also have plenty of eyebrow clearance where the relief gets closer to the valve on the side of the piston.
Motor is pretty much done FINALLY! Just need to finish installing the cam and primary cover and anything that hooks to them or runs through them. I still need to install all of the oil lines, ignition, starter, oil tank and make up some spark plug wires.